Emily Garatoni
(574) 309 – 7281
____________________________________________________________________________________________________________________________________________________
Permanent Address:
2802 Danzig Place,
Louisville, KY 40245
egaraton@purdue.edu
____________________________________________________________________________________________________________________________________________________
Objective:
To acquire a full time career as an assistant project manager working in unique opportunities that will challenge and develop my skills as a
professional.
Education:
Purdue University
Bachelor of Science
Major: Building Construction Management
Minors: Electrical Construction and Organizational Leadership & Supervision
Skills & Coursework:
• Computer Skills – AutoCAD, Contract Manager, Microsoft Office, Primavera 6, Prolog Converge, Revit Architecture
• Building Materials & Methods, Estimating, Project Management, Safety, Scheduling, and Site Supervision
• OSHA 30 Hour Certification
•
____________________________________________________________________________________________________________________________________________________
Summer 2015
Intermediate level Spanish speaker
Work Experience:
Valiant Construction
Barton Malow
•
• Assistant Project Manager
o Assisted in project startup procedures and communication
o Created subcontract agreements, purchase orders, and change orders
o Compiled project manuals and other informational records
o Created a subcontractor schedule and assisted in monthly project schedule updates
GPA: 3.2
Graduation: May 2015
Summer 2014
PayneCrest Electric
•
Project Engineer
o Worked proficiently with Contract Manager and Prolog Converge programs
o Created, reviewed, and recorded information regarding submittals, requests for information and daily field reports
o Attended weekly meetings with the client for construction schedule review and activity planning
o Assisted during weekly meetings for 3D coordination of MEP systems with subcontractors
o Accompanied project manager in contract and cost review meetings with the client
o Participated in weekly site walks with Safety to analyze issues and implement alternative methods
Summer 2013
• Engineering
o Designed and altered project material and systems layout on AutoCAD
Project Management
Majority Builders Inc.
•
o Read and interpreted electrical drawings
§§ General electrical prints, system design and connection prints, material coding
o Created demolition, installation, and detail drawing sets for general foremen and project managers
Project Management
o Thorough comprehension of construction drawings and specifications
o Collaborated with subcontractors to create purchase and change order forms
o Followed the necessary steps per the city to obtain building permits
o Performed jobsite walkthroughs with subcontractors, clients, and utility representatives
o Created project schedules and project progress reports
•
•
o Assisted head superintendent in site visits to collaborate and implement solutions to unforeseen conditions
____________________________________________________________________________________________________________________________________________________
•
Site Supervision
Activities:
• Habitat for Humanity
•
Ireland – BCM Study Abroad
Fall 2011 -‐ Present
Summer 2013
Estimator
o Developed a familiarity with hard bid and design-‐build projects and attended bid openings
o Composed proposals, estimated a storage building, and gave formal presentation
Safety Supervisor & Site Work
o Visited sites for safety inspections
o Analyzed soil types for site planning
o Assisted work on site for foundation installation and miscellaneous carpentry